Getting a bit done this morning. I am working from the noes back.
Noes cone is done with bats, telemitry, ASI (pitot tube).
I chose to put the pitot in the noes for eas of access and installation.
Reciever bats are mounted here and run back to the volt regulator.
The UP3 valve is plumbed and I tested the front gear doors and noes retract before I move on. The door and gear work great, just needs 20-30 lb to slam it down. I slowed down the gear as it was fallowing the gear door almost simultaneous. Smart fly board is under the main tray and I may put some more stuff under there.
I need to install the break valve and the gear failsafe next to complete this section. I will layout the main board next.
TB